Created page with "{| class="wikitable" |序号 |账目 |增减额 |全兴累计应收 |说明 |- |1 |33#楼工程价款 |21,747,501.00 |21,747,501.00 |已全部到期 |- |2 |5#地下车库工程价款 |3,902,867.43 |25,650,368.43 |鉴定调整后造价 |- |3 |减:车库未到期3%质保金 |−117,086.02 |25,533,282.41 |暂未到期,并非消灭 |- |4 |减:江风已付工程款 |−24,657,039.26 |876,243.15 |双方无争议 |- |5 |减:全兴承担水电费 |−54,360.74 |821,882.4..." |
No edit summary |
||
| Line 1: | Line 1: | ||
{| class="wikitable" | {| class="wikitable" | ||
!序号 | |||
!账目 | |||
!增减额 | |||
!全兴累计应收 | |||
!说明 | |||
|- | |- | ||
|1 | |1 | ||
Latest revision as of 14:58, 21 July 2026
| 序号 | 账目 | 增减额 | 全兴累计应收 | 说明 |
|---|---|---|---|---|
| 1 | 33#楼工程价款 | 21,747,501.00 | 21,747,501.00 | 已全部到期 |
| 2 | 5#地下车库工程价款 | 3,902,867.43 | 25,650,368.43 | 鉴定调整后造价 |
| 3 | 减:车库未到期3%质保金 | −117,086.02 | 25,533,282.41 | 暂未到期,并非消灭 |
| 4 | 减:江风已付工程款 | −24,657,039.26 | 876,243.15 | 双方无争议 |
| 5 | 减:全兴承担水电费 | −54,360.74 | 821,882.41 | 从工程款中扣除 |
| 6 | 减:临时道路分担费 | −76,000.00 | 745,882.41 | 从工程款中扣除 |
| 7 | 减:保险费 | −38,475.50 | 707,406.91 | 法院按总造价1.5‰认定 |
| 8 | 按判决主文取工程款 | — | 707,406.00 | 判决金额优先于精确计算 |
| 9 | 加:江风承担鉴定费 | 15,000.00 | 722,406.00 | 全兴已预交 |
| 10 | 减:全兴承担工期违约金 | −300,000.00 | 422,406.00 | 江风反诉胜诉金额 |